Current Restoration Schedule
The full schedule is below in the SCHEDULE link. In general, we will be re-roofing two buildings at a time, taking 3-days per group of two.
Project stagging and supply delivery- 3/27/2023
Buildings
Building #2 and Building #3 (8321 & 8327)
Roofing- 3/28/2023 through 3/30/2023
Building #4 and Building #6 (8331 & 8337)
Roofing- 3/31/2023 through 4/4/2023
Building #5 and Building #7 (8341 & 8347)
Roofing- 4/5/2023 through 4/7/2023
Garages
Garage 1 and 2- 4/8/2023
Garage 3 and 4- 4/11/2023
Garage 5 and 6- 4/12/2023
Important Notices
Notice: When emailing CCMG please include your unit number in the subject section of the email.
Communications
In general, please follow this communication tree starting at the top and working down if you need to get ahold of the project managers.
Kendra – Bone Dry Site Supervisor
|765-481-1529
Ulises – Bone Dry Site Supervisor
970-413-4915
Josh Reeths - Bone Dry Roofing superintendent.
Josh.reeths@bonedry.com
Evan Daugherty-Bone Dry Roofing Project Manager
Evan.daugherty@bonedry.com
(303) 332-8164
Spencer Shaw- CCMG General Contractor
spencer@ccmgpro.com
(860) 733-3435
Scott Benglen-CCMG Partner
scott@ccmgpro.com
(303) 596-6043