Storage container and equipment will be delivered starting June 12th.
Port-a-Potty delivery June 13-14
Roofing Materials will begin being delivered June 14th for buildings 1-4 on the map
Please keep the interior parking spots clear starting 6/12/2024 at 8am.
Reroofing construction will begin June 17, 2024.
Please click on the map link below to see a general flow of construction work throughout your community.
Buildings
Buildings 1-4 re-roofing will begin June 17th and are scheduled to be completed within 3 days.
Buildings 6-8-10-12 re-roofing will begin June 18th and will be completed in two days.
Anticipated schedule (best case, no weather):
Monday (6/24) – #5, 7, 9, 11
Tuesday (6/25) – Finish #9, 13, 15, 17, maybe start 18 depending on #9 completion
Wednesday (6/26) – 17, 18, 21, 22
Thursday (6/27) – 18, 20
Important Notices
No parking in the interior spots starting June 12th at 8am.
The construction map and a full community letter will be posted here by June 12, 2024.