Happy Friday Cherry Creek Village, here’s your update for 1/31/2024

Buildings 1, 14, 12, and 13 are completed. Weather yesterday slowed us down a bit, so we had a late start. We completed  all of the little shed buildings yesterday, rather than start anything new after losing time in the morning. Here is the anticipated schedule going forward: 

1/31 – 2/1 (Friday, Saturday) complete buildings 2, 10, 11

2/3 -2/4 – Buildings 7, 8, 9

2/5-2/7 – Ground drop materials for Clubhouse, 5, 6. Complete #4, 5, 6, clubhouse. 

Assuming we don’t get any weather delays, we should be completed by the end of next week. 

CCMG Contact Information

CCMG Site Superintendent/Project Manager
Brent Egger (720) 633-6615
Yellowhammer.co@gmail.com

CCMG Partner
Scott Benglen
(303) 596-6043
Scott@ccmgpro.com

Important Notices

Notice: When emailing CCMG please include your unit number in the subject section of the email.

Communications

In general, please follow this communication tree starting at the top and working down